San Diego County Psychiatric Hospital Building Assessment

Program overview

Vanir staff performed a building assessment of the San Diego County Psychiatric Hospital, a 109-bed facility originally constructed in 1958, to determine compliance with The Joint Commission Life Safety (NFPA 101) codes and the 2009 and 2018 editions of the Environment of Care (NFPA 99). For this effort, our team conducted the following:

  • Reviewed annual MEP inspections on building systems (performed by outside contractors), and preventive maintenance program (performed by Facilities Maintenance engineers)
  • Reviewed/updated several administrative programs with Hospital Administrators and Facility Manager: Emergency Operational Plan, Medical Equipment Management Plan, Site Evacuation Plan, etc.
  • Reviewed/updated fire protection tests forms to meet NFPA 25
  • Inspected emergency generator, automatic and manual transfer switches, lighting systems, exit signs and medical equipment
  • Performed Fire Life and Safety survey of 169 fire-rated 20 minutes doors; smoke barriers doors; lights for egress, exit signs; and self-closing or automatic closing devices on smoke barriers doors
  • Presented recommendation for repairs and drawings with door IDs and location, establishing an inventory for maintenance program
  • Presented barrier monitoring ideas to improve tracking of barrier maintenance and penetrations
  • Wrote addendum to existing Building Maintenance Program to include the program for maintenance of fire barriers, as an option
 
 
 
San Diego, California
County of San Diego
Square Footage
63,229 SF
Completion Date
2018