Photo Credit: HR Group Architects

Lincoln Operations Center

Project overview

Vanir provided construction management services for the Lincoln Operations Center, a new 35,900 square-foot and two-level tilt-up (precast) concrete facility. Situated on a 3.3-acre site, it includes three major components:

  • A control center
  • A data center
  • Business continuity areas

The facility’s function is considered “mission critical” in nature and has the structure, equipment anchorage and seismic bracing designed to meet California Essential Services, Category IV building requirements. The facility is supported by backup standby generation power.

 
 
 
Lincoln, California
Confidential
Architect

Gensler, HR Group Architects

Criteria Architect: Vanir

Contractor

Turner Construction

Square Footage
35,900 SF
Construction Cost
$19.3 Million
Start Date
2014
Completion Date
2016