Program overview
Vanir was selected to provide program management services for Conejo Valley Unified School District’s Measure R Modernization and New Construction Program, based on our construction management services for two of the District’s 400-seat performing arts centers in 1997, both of which were completed with less than 2% change orders.
Our work included master scheduling, budgeting and construction management services for 31 campuses. Our value engineering, change order negotiation and schedule analysis for the entire program kept it running smoothly and all project objectives were met.
Following the completion of Measure R in 2007, Vanir continued to provide construction management services for ongoing modernization efforts. In 2014, we assisted in the successful pursuit of the District’s $197 million Measure I Bond and contributed to the development of the master planning program.