Anschutz Outpatient Pavilion

Vanir developed the project management plan, policies and procedures for the design and construction of the Anschutz Outpatient Pavilion facility, as well as the campus master schedule, which included the Outpatient Pavilion, Cancer Center, Eye Institute, Site Utilities (infrastructure) and Central Utility Plant.

Fast-Track Success

This fast-track design-build project was completed within budget and took only 22 months from design to occupancy; two months ahead of the already aggressive schedule of 2 years.

Effective Value Engineering, Estimating and Negotiating

Through value engineering sessions, estimate reviews, and guaranteed maximum price negotiations, Vanir was successful in reducing the construction budget by 13 percent and completed the project with less than one percent in change orders.

Location

Aurora, CO

Client

University of Colorado Hospital Authority

Design Team

(Design-Build) Architects: - HDR - Haller & Larsen Contractor: - Phipps / McCarthy

Construction Cost

$80 million

Completion

2001

Size

475,000 SF