Successful Construction Management of Difficult Project
Vanir's constructability review, bid marketing campaign, and onsite construction management
and inspection services led to the successful delivery of this complicated project. The
marine outfall project included:
Overcoming Challenges
Marine projects (such as this) present unusual challenges due to the combination of
constraints from permitting agencies, local jurisdictions and natural conditions. To help
manage this, Vanir created a comprehensive table that identified all constraints and
requirements in an abbreviated format that grouped constraints into specific areas of work.
This was distributed to and discussed with the project team prior to starting construction.
In-water work had to be scheduled within the "fish window" timeframe established by the Hydraulic Project Approval (HPA) Permit, issued by the Washington State Department of Fish and Wildlife. Beach work had to be scheduled around tides and the beach had to be protected from damage during construction. Eelgrass had to be harvested prior to sheet pile installation in the eelgrass zone, maintained during construction, and re-planted after construction.
The upland and intertidal work took place in the summer of 2007 on a popular local beach park near a marina. The project team had to find the proper balance of safety and access to meet the needs of the public. Community relations was an important part of our onsite inspector's job. The project was substantially complete on September 30, 2007 with the tie-in of the new outfall pipe to the wastewater treatment plant.