|
|
|
|
|
|
|
|
|
|
Vanir was selected to provide construction management and inspection services for
the New Dock Street/Henry Ford Grade Separation project, which provided a
grade-separated rail access to the port facilities on Terminal Island and the APL
and LAXT freight terminals. The project consisted of constructing two new grade
separation bridge structures, depressed roadways, approach ramps, street
realignment and paving, temporary and permanent railways, lighting, signage and
striping, grading and fill, stone columns, retaining walls and utility relocation
during construction.
The Partnering agreement employed by the Port of Los Angeles on this contract
provided a valuable resource for dealing with significant unforeseen conditions
that arose during the course of construction. Change orders were issued for
providing the excavation and removal of unsuitable soils replaced by rock; the
removal and disposal of hydrocarbon contaminated soils and the construction of a
$2.5 million dollar pump station to accommodate storm water runoff. The
additional work added 169 days to the construction schedule, which the Port of Los
Angeles elected to offset by accelerating the contractors schedule by 123 days at
a cost of $2.3 million dollars. The proactive construction management implemented
on the project reduced the actual completion date by 29 days and limited the
increased cost to the contract by 5.73%.