Delivery of New Healthcare Facility
The Anschutz Inpatient Pavilion is a new, 12-story healthcare facility including:
We Helped Negotiate the GMP to Below Budget
Vanir assisted the University Hospital with the preparation, review, and negotiation of the
architect and the CM/GC contracts, the negotiation of the Guaranteed Maximum Price (GMP),
and estimate coordination. The GMP was negotiated to below the owner's budget.
Our staff also reviewed the contractor's schedule and assisted in the preparation of the
project master schedule and reviewed monthly updates.